Welcome back to Episode 8 of the Perlo Podcast! Podcast host Elissa Looney, Director of Strategic Initiatives at Perlo Construction, is joined by Devin Koopman, Vice President of Construction, and Joe York, General Superintendent. In today’s podcast, we’re going to explore site logistics in construction, which are a critical piece of the planning and execution of construction sites.
Site logistics can be thought of as the foundation that sets up an efficient and safe construction site while making the process easy and keeping the project on schedule. It involves factors such as:
Devin notes that schedule logistics are rarely shown in the drawings and often don’t get as much attention as they require. It is critical to be proactive and consider all items of a project when planning site logistics.
Preconstruction efforts are the “recipe” for an effective project. When preconstruction takes place, we look at the current plan and drawings for the current site logistics and try to understand what the end result will be. Logistics range from job to job and are a huge factor in a successful project outcome.
When considering the current climate of supply chain issues and long lead times, it may be necessary to procure materials early. In this case, project teams must be able to purchase or lease extra land offsite to hold materials. Joe explains that our teams have had to get creative and think outside of the box to find additional storage area for materials.
Elissa adds that having space for materials shortage has become a much bigger factor in today’s day and age, as companies aren’t able to get “just-in-time” delivery if they want to guarantee that they will receive the materials on time.
“The fact is that there aren’t as many large lots for people to develop anymore,” remarks Joe. He elaborates that because of this, it can be difficult to find space to lay down materials, park trucks and trailers, and actually build the building.
According to Joe, “if you can’t get a neighboring property to make your footprint larger for the build, you’ve got to get creative.” Planning ahead for these aspects of a project gives teams more opportunity to be innovative when utilizing space and being proactive when addressing potential issues.
How Do We Use Site Logistics to Create Efficiencies on Jobsites?
Devin uses an example about concrete to answer this question, noting that here at Perlo, “we like to pour concrete, and we like to pour a lot of it.” He goes on to explain that often times, our teams conduct concrete pours at 2AM to maximize efficiencies. Early morning pours are great, according to Joe, because there is no traffic and the concrete gets poured before the weather gets too hot in the summertime. When there are anywhere from 50-70 trucks expected to come and go from your project with concrete at a dark hour, site logistics become that much more important. Factors to be considered can range from how to get the trucks in and out to where the pump trucks need to be staged and even accommodating for residential neighborhood time restrictions. “Time is money, so you need to get them in and off your site as quickly as possible,” explains Devin.