Connectologists® Pete Aston, Kyle Murchie, and Alex Ikonic explore the mounting pressures developers face as Gate 2 offers arrive. Transmission offers have three months to accept but queries must be submitted within four weeks. Distribution offers are expected to have about four weeks, though this may vary between DNOs. Securities are due approximately 30 days after acceptance.
The key challenges developers are facing:
Critical next step: Don't put accepted offers "on the shelf"—immediately engage to confirm design progression, payment requirements, and where projects sit in TO gating windows.
We understand the complexity of grid connection challenges, and the Connectologists® hope these insights help developers navigate Gate 2 with greater clarity.
Recorded: 12 November 2025