Listen

Description

The construction bidding process for public projects is one of the most confusing topics for AEC professionals who've never worked on publicly bid work.

In this episode, we break down the entire procurement journey from completed drawings to breaking ground, step by step.

Michael Riscica shares first-hand experience from both sides of the process, first as an architect on public projects and then as a government project manager responsible for hiring architects, contractors, and engineers.

You'll learn the 8 key stages of the construction bid process, the role of the procurement department, how sealed bidding and bid openings actually work, and why this process takes 2-3 months from finished drawings to construction start.

📝 Key topics covered:

⏱️ Chapters:

(0:00) Introduction

(1:41) The Big Picture: Timeline Overview

(5:04) Key Stages of the Process

(6:26) Bid Preparation

(8:00) Advertisement

(9:06) Bidding Period

(11:49) Bid Submission and Opening

(13:12) Evaluating the Bids

(14:27) Contract Formation

(15:41) From Award to Breaking Ground

(16:51) Notice to Proceed (NTP)

(18:35) Common Challenges

(20:30) Conclusion

📖 Read the full blog post and grab your free 2-page study notes: Construction Bidding Process: Navigating Public Projects

📝 Free PDF Study Notes: Download Free Bidding Process Study Notes

🎯 ARE Boot Camp - 10-Week Coaching Program

🎯 ARE 101 Membership - All ARE Study Materials

📚 Individual Courses: